Consideration was given to a report on the progress on enforcement cases where enforcement action had been authorised.

 

The Council’s Development Management Team Manager, Elaine Moulton updated Members with regard to 5 Boggs Cottages advising that a date had been set for proceedings for 23 February, 2022.

 

With regard to the barn at Moss House Farm, Bignall End, Elaine Moulton advised that the Enforcement Notice Appeal Hearing had commenced today and would conclude tomorrow.

 

Hazeley Paddocks was awaiting an appeal decision.

 

Church View Farm, Harriseahead had gone beyond the due notification date.  The requirement to remove the silo within the month was in the past.  It was believed that the silo had now gone but needed to be clarified.  A site visit would take place this coming Thursday.  If the Notice had not been complied with, compliance would be sought through the appropriate means.

The Chair requested that, if the silo had not gone, an information item be put onto the next agenda to advise Members.

 

Land adj Offley Arms.  This was still within the period where an appeal could be lodged – up until 19 November

 

In the last couple of days, a draft Notice had been received for Domvilles Farm, which would be checked and issued.  Within the next two weeks a draft Notice should be received for Robert Coates Plant Hire.

 

 

Resolved:                       (i)         That the information be received.

 