KIDSGROVE SPORTS CENTRE

Meeting: 09/06/2021 - Cabinet (Item 115)

115 KIDSGROVE SPORTS CENTRE REFURBISHMENT pdf icon PDF 452 KB

Decision:

That Cabinet:

 

1. Notes the progress made on the project since the March 2021 Cabinet meeting in terms of scope, design and budget in consultation with the Kidsgrove Leisure Centre Community Group.

2. Notes that expenditure to date is £1.063m.

3. Notes that the Kidsgrove Town Deal funding allocation announced by MHCLG on the 3rd March including £2.45m towards the overall cost of the project has now been confirmed as guaranteed funding by MHCLG on 10.05.21.

4. Approves the overall capital cost of the project is £7.5m (which includes the works undertaken to date on site and the funding, including external funding sources, for the scheme is contained in section 8.1).

5. Approves the revenue support from the Council for the scheme for the first five years of the sport centre operation to the Community Group – Kidsgrove Sports Centre – is £480k worst case scenario.

6. That a further contract award is given to Willmott Dixon Construction Ltd for the amount of £6.437m to complete the works in readiness for opening in May 2022.

7. Authorises the Executive Director – Commercial Development and Economic Growth, in consultation with the Portfolio Holder, One Council, People and Partnerships to take such actions and enter such agreements as are reasonably necessary or prudent to ensure the refurbishment is complete and the centre operational by the target date.

Minutes:

Cabinet considered a report on the refurbishment of Kidsgrove Sports Centre.  The report noted that progress since the last report to Cabinet in March 2021 included:

·         Confirmation from Willmott Dixon Construction Limited that the overall target cost for the scheme was £7.5m (which included all works undertaken to date).

·         The Community Group had confirmed that the first five years of operation would require £480k of revenue support from the Council in the worst case scenario.

·         The lease for the Sports Centre had been issued to the Community Group and agreed in principle.

·         Successful discussions had taken place between the Community Group and the Kings Academy on sharing of facilities and the undertaking to jointly appoint a facilities manager who would work across both sites/operations.

 

Resolved: That Cabinet:

 

1. Notes the progress made on the project since the March 2021 Cabinet meeting in terms of scope, design and budget in consultation with the Kidsgrove Leisure Centre Community Group.

2. Notes that expenditure to date is £1.063m.

3. Notes that the Kidsgrove Town Deal funding allocation announced by MHCLG on the 3rd March including £2.45m towards the overall cost of the project has now been confirmed as guaranteed funding by MHCLG on 10.05.21.

4. Approves the overall capital cost of the project is £7.5m (which includes the works undertaken to date on site and the funding, including external funding sources, for the scheme is contained in section 8.1).

5. Approves the revenue support from the Council for the scheme for the first five years of the sport centre operation to the Community Group – Kidsgrove Sports Centre – is £480k worst case scenario.

6. That a further contract award is given to Willmott Dixon Construction Ltd for the amount of £6.437m to complete the works in readiness for opening in May 2022.

7. Authorises the Executive Director – Commercial Development and Economic Growth, in consultation with the Portfolio Holder, One Council, People and Partnerships to take such actions and enter such agreements as are reasonably necessary or prudent to ensure the refurbishment is complete and the centre operational by the target date.