KIDSGROVE SPORTS CENTRE REFURBISHMENT

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

(i)            The progress made on the project since April 2020 Cabinet in terms of scope, design and budget in consultation with the Kidsgrove Leisure Centre Community Group be noted.

(ii)          It be noted that following detailed survey work, the target cost of the project is now £5.998m

(iii)         The submission of a bid under the Town Fund Advance Funding for a contribution towards the refurbishment of the Centre be noted.

(iv)         A supplementary capital estimate be approved of up to £400,000 to be drawn down from the Council’s 2020/21 capital programme contingency in the event that external funding contributions cannot be secured

(v)          That the Executive Director Commercial Development and Economic Growth, in conjunction with the Portfolio Holder for Corporate and Service Improvement, People and Partnerships, continue to work with the Community Group to progress the refurbishment.

Publication date: 09/09/2020

Date of decision: 09/09/2020

Decided at meeting: 09/09/2020 - Cabinet