Application for Minor Development - Land Adjacent to Sainsburys Store, Liverpool Road; Marston Inns and Taverns & Wildgoose Construction / Peacock and Smith; 13/00807/FUL
Minutes:
Resolved:
That the application
be permitted subject to conditions concerning the following
matters:
- Commencement within three years.
- Approved
plans.
- Prior
approval of materials.
- Levels to
be in accordance with approved plans unless otherwise
agreed.
- Provision
of a fence or other barrier to prevent access between the proposed
development and the rear of properties on Ashfields New Road in accordance with details to be
agreed. The barrier should be
from the corner of the building to the corner of the rear boundary
of 1 Ashfields New Rd (with any gate
necessary to achieve appropriate means of emergency exit from the
premises to be alarmed to prevent unauthorised use)
- Hard and
soft landscaping to be carried out in accordance with the approved
details. Landscaping to
include additional planting to the rear of the development behind
Ashfields New Road.
- Provision of access,
parking, servicing and turning areas before the development is
brought into use.
- Prior approval of
surfacing materials, surface water drainage, and delineation of
parking and servicing areas.
- Any gates to be a
minimum of 10m rear of the Sainsbury’s access road and shall
open away from the highway.
- Prior approval of a
Construction Method Statement to include details of the site
compound; access for construction vehicles; the parking of vehicles
of site operatives and visitors; loading and unloading of plant and
materials; storage of plant and materials; and wheel wash
facilities.
- Prior approval and
provision of secure weatherproof cycle
parking.
- Implementation of noise mitigation measures as set out in the
submitted Noise Assessment, and/or as recommended by the
Environmental Health Division.
- That bottles are not emptied outside beyond
19:00hrs,
- Prior approval of
details of facilities to prevent the deposition of extraneous
matter (mud, debris, etc.) on the public highway before
commencement of development and implementation in accordance with
the approved details.
- No machinery to be
operated or process to be carried out in the construction of the
development, and no construction traffic to enter or leave the site
between 1800 hours and 0700 hours Monday to Friday, and not at any
time on Sundays, Bank Holidays or after 1300 hours in
Sundays.
- The residential
element shall remain in the same ownership as the commercial
activity unless otherwise approved by the Local Planning Authority
(LPA).
- Construction, glazing
and ventilation of the residential element to be in accordance with
the Noise Report.
- Noise mitigation
measures for the mechanical services servicing the development to
be in accordance with the Noise Report.
- Installation of a
noise limiting device, to be maintained thereafter, to control
internal noise levels from amplified music to the level agreed by
the LPA.
- Deliveries restricted
to between 0700 and 2100 hours on any day.
- Acoustic screen to be
erected prior to commencement of commercial activities in
accordance with the details in the Noise Report.
- Noise mitigation
measures for deliveries as set out in the Noise Report shall be
employed.
- Empty bottles to be
stored and handled, and presented for collection as set out in the
Noise Report.
- Means to prevent
grease, fat and food debris from entering the foul drainage system
to be implemented in accordance with approved details.
- Prior approval of an
odour abatement system for the kitchen before commencement of
development and implementation in accordance with the approved
details. Cooking process to cease at
any time the extraction system fails to operate.
- Submission and implementation of a lighting
assessment.
Supporting documents: